To approve the strategic direction to procure
2 x Asset Delivery Partners (North and South) that will manage and
administer major works and statutory compliance work programmes;
and broaden the client technical skills base.
Two technical delivery partnerships (North and South – 3-year
duration) with two principal functions:
a) Specify and manage major work projects (planned and procured by
the strategic asset partner – using the DPS).
b) Empower and train the client team to self-manage major work
projects (removing the continuous reliance on third-party
consultants).
Decision type: Key
Reason Key: 2. Financial;
Decision status: For Determination
Wards affected: (All Wards);
Notice of proposed decision first published: 13/08/2021
Decision due: Not before 11 Sep 2021 by Cabinet Member for Better Homes and Reducing Homelessness
Lead member: Cabinet Member for Better Homes and Reducing Homelessness
Lead director: Strategic Director: Resident Services
Department: Resident Services
Contact: Andrew Jacques, Head of Contract Scrutiny and Cost Management Email: AJacques@lambeth.gov.uk.