Willmott Dixon has been procured as the
preferred bidder for the delivery of the new 5FE Secondary
Department and 150 place Sixth From at Woodmansterne School.
The programme to deliver the new school is very challenging and in
order to mitigate some of the delay, it is proposed to engage
Willmott Dixon early in the process to undertake some enabling
works, works deferred from the primary school project and to
complete some of the external works and drainage.
Its also proposed to engage with Willmott Dixon earlier in the
design process including progressing with surveys and detailed
design development. This will enable an early start of the
construction works in parallel with the Pre-Contract Agreement
being signed and the award of the main contract to Willmott
Dixon.
Willmott Dixon will be asked to provide 3 quotes for each package
of works to be awarded (as per the terms of the SCF Framework
Agreement).
Decision type: Key
Reason Key: 2. Financial;
Decision status: Abandoned
Wards affected: Streatham South;
Notice of proposed decision first published: 17/02/2017
Decision due: Not before 20 Mar 2017 by Deputy Leader of the Council (Housing and Homelessness)
Lead director: Strategic Director: Neighbourhoods and Growth
Department: Neighbourhoods & Growth
Contact: Peter Dawes, Consultant, Major Capital Programmes Email: PDawes@lambeth.gov.uk.