The decision will enable the contract to be
raised and the works undertaken. The works will include internal
and external refurbishment and remodelling works as required. The
works will also include the provision of a new 30-place nursery
along with the demolition of the existing caretaker’s
house.
The annual budget for the proposed works will result in the spend
of circa £2.5M excluding FFE and ICT equipment.
The request for approval to appoint the successful tenderers for
the construction contract will be presented in May 2014.
Decision type: Key
Reason Key: 2. Financial;
Decision status: Recommendations Approved
Wards affected: St Leonards; Streatham South; Streatham Wells;
Notice of proposed decision first published: 03/01/2014
Decision due: 13 Oct 2014 by Deputy Leader of the Council (Finance and Resources)
First appeared on forward plan: 3 January 2014
Lead member: Deputy Leader of the Council (Finance and Resources)
Lead director: Strategic Director: Neighbourhoods and Growth
Department: Neighbourhoods & Growth
Contact: Alfred Akpo-Teye, Programme Manager Email: aakpo-teye@lambeth.gov.uk Tel: 020 7926 9839.
Consultation process
Consultation with key stakeholders / schools
etc. has been on-going. During a process of feasibility the school
and stakeholders have been informed of the nature of the works
required. Once the Architects have produced a design, public
meetings will be held at the school and all stakeholders invited.
Informal consultation with all stakeholders will be followed by a
statutory consultation.
Consultees
Schools
Stakeholders