Decision details

Cycle Storage on Housing Estates

Decision Maker: Cabinet Member for Sustainable Transport, Environment and Clean Air (job-share)

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

1.          To approve the spending of £500,000 Capital Investment Programme approved by Cabinet on 20 July 2020 over five years to fund the provision cycle storage capacity on housing land.

 

2.          To approve the proposed cycle hangar design (Appendix A) for future installation of hangars and roll back the existing Cyclehoop breadbin type installations on housing estates.

 

3.          To approve the proposed AskPorter system development and associated costs to enable the necessary administrative improvements required to provide a cost-effective service.

 

4.          To approve the procurement of a supplier to deliver installations as per the prescribed design specifications.

 

 

Publication date: 12/08/2021

Date of decision: 20/08/2021

Effective from: 01/09/2021