Decision details

Statutory Consultation Objections to installation of Cycle Hangars within Controlled Parking Zones (CPZs)

Decision Maker: Assistant Director, Parking, Street Management and Commercial, Environment and Streetscene

Is Key decision?: No

Is subject to call in?: No

Decision:

(1)       Following consideration of representations and objections received during statutory consultation detailed in this report (set out in Appendix B), to make traffic management orders facilitating the installation of 18 cycle hangars and relocation of one hangar at the locations set out in Appendix A, at a total cost of £9,310.

 

(2)        To have regard to the Equality Impact Assessment prepared for the purposes of this report (Appendix C)

 

(3)        To exercise discretion not to hold a public inquiry pursuant to Regulation 9 of the Local Authorities Traffic Orders (Procedure) (England and Wales) Regulations 1996.

 

Publication date: 02/09/2021

Date of decision: 10/09/2021

Accompanying Documents: