Decision:

1.    To issue scheme approval for the Quietway 5 schemes around Clapham Common, as detailed in Tables 1, 4, 5, 6, 7 and 8, at a forecast cost of £300,000.

 

2.    To agree to these schemes’ implementation under Section 6, 124 and Part IV of Schedule 9 of the Road Traffic Regulation Act 1984 (as amended), section 90 of the Highways Act 1980, and Article 17 of the Ministry of Housing and Local Government Provisional Order Confirmation (Greater London Parks And Open Spaces) Act 1967, subject to no material objections resulting from consultees.

 

3.    That in the event of a material objection being received to the statutory consultation a report be considered by the Director of Environment in consultation with the Cabinet Member for Environment and Clean Air.

 

4.    That works to Bromell’s Road proceed, but that TfL be requested to allocate a further £105,000 to the Quietway 5 project and that no further works start without written confirmation from TfL that they will meet all the council’s costs for construction.

 