Award of the Council’s Corporate Gas and
Electricity Supply Contracts
1. To approve the continued use of the CCS Energy Frameworks to obtain providers for the supply of gas and electricity to cover the 12 month period 1 April 2019 to 31 March 2020 for an estimated total cost of £9,000,000.
2. To approve the use of CCS’ appointed energy framework suppliers for the supply of gas and electricity to cover the 12 month period 1 April 2019 to 31 March 2020. The breakdown of contract spend between the appointed suppliers is estimated at; EDF Energy (large electricity supplies and street lighting) £1,500,000, British Gas Business (smaller electricity supplies) £4,000,000, and Corona Energy (corporate gas supplies) £3,500,000.
Publication date: 13/09/2018
Date of decision: 21/09/2018